(Redirected from Deep Tunnel Project)
The 'Tunnel and Reservoir Plan' (abbreviated 'TARP' and more commonly known as the 'Deep Tunnel Project' or the 'Chicago Deep Tunnel') is a large
civil engineering project that aims to reduce flooding in the metropolitan
Chicago area, and to reduce the harmful effects of flushing raw
sewage into
Lake Michigan by diverting storm water and sewage into temporary holding
reservoirs. The
megaproject is one of the largest
civil engineering projects ever undertaken in terms of
scope, cost and timeframe. Commissioned in the mid-1970s, the project is managed by the
Metropolitan Water Reclamation District of Greater Chicago. Full completion of the system is not anticipated until
2019, but substantial portions of the system have already opened and are currently operational. Across 30 years of construction, over $3 billion has been spent on the project.
[ WGN-TV CoverStories: Deep Tunnel Sanders, Steve ]
History
1800s
The Deep Tunnel Project is the latest in a series of civil engineering projects dating back to
1834. Much of the problems experienced by the city of Chicago are directly related to its
topography and the fact that city is largely built upon a
marsh. The
Chicago River was ineffective in carrying sewage away from the city; when it did, the earliest water pumps in Lake Michigan that provided drinking water to Chicagoans became clogged with sewage. These conditions led to frequent
cholera epidemics in the 19th and early 20th centuries.
[ Flood Control and Drainage Juhl, Arland R. ]
In
1871, the
Illinois and Michigan Canal was built, diverting some sewage water from the Chicago River. In 1900, to improve general health standards, the flow of the main branch of the Chicago River was reversed to drain water from
Lake Michigan, as opposed to having the river flow into Lake Michigan. This further improved the sanitation of Lake Michigan, and helped to prevent further cholera epidemics.
1900s
The construction of the
Sanitary and Ship Canal (1892-1900), enlargements to the
North Shore Channel (1907-1910), the construction of the
Cal-Sag Channel (1911-1922) and the construction of
locks at the mouth of the Chicago River (1933-1938) brought further improvements to the sanitary issues of the time. These projects blocked further amounts of sewage from draining into Lake Michigan. The projects also brought fresh lake water to inland waterways to further dilute sewage that was already in the waterways.
Surrounding farmland also engaged in flood control projects. The
Illinois Farm Drainage Act of 1879 established
drainage districts. These districts were generally named for the basin they drained — for example, the
Fox River Drainage District. After
World War II, suburban communities began to realize the benefits of separating
stormwater from sewage water and began to consturct separate sewer and storm drainage lines. The primary benefit of wastestream separation is that storm water requires less treatment than sewage before being returned to the environment.
Flood damage grew markedly after 1948, when surrounding drainage areas were lost to development and human activity. Serious flooding has occurred in the Chicago metropolitan area in the years 1849, 1855, 1885, 1938, 1952, 1954, 1957, 1961, 1973, 1979, 1986, 1987, and 1996 — but most record-setting
crests have been set after 1948.
In the 1960s, the concept of Deep Tunnel was studied and recommended as a solution to continuing flooding issues. The Deep Tunnel system would be built as a network of 109 miles (197 km) of tunnels of varying width.
Current status
As of October 2005, substantial drilling and blasting for the underground tunnels was complete. Reservoirs are scheduled to become operational and hold and process sewage, notably in
McCook (2013 and 2019) and
Thornton (2014). Currently, water travels to the
Thornton Transitional Reservoir, which will be abandoned in 2014. Water is also stored and held in the tunnels themselves while sewage treatment plants release treated water into the
Calumet and
Des Plaines Rivers.
Mining work was completed on the Little Calumet leg of the Deep Tunnel System, and final connections were scheduled for completion on
March 1 2006. The Little Calumet leg is in length. Operation of the Little Calumet leg will mark the total completion of all of tunnel included under Phase I of the TARP project, and the culmination of 30 years of tunnel construction. Stretching beneath
Cook County, the tunnel is in diameter, lined with concrete and is located at a depth of to below ground in limestone rock.
Effects
Severe weather events as recent as the early 1990s have forced water management agencies to pump excess wastewater into the lake and river in order to prevent flooding. These incidents have been reduced as more of the Deep Tunnel system has become operational. Long considered an open sewer, the Chicago River now hosts more than 50 species of fish and increased wildlife along its shores. Riverfront property has begun to be classified more as an asset than a liability, and substantial development is occurring along many portions.
Canoeing is once again allowed on the waterway, but
swimming is still prohibited due to high pollution levels.
In the mid 1990s, a heavy
thunderstorm drenched the southern portion of the Deep Tunnel area with several inches of rain in short period of time. While the Deep Tunnel system performed satisfactorily by absorbing excess water, water within the system itself rushed north to the reservoirs at
O'Hare International Airport and the
Bahá'í Temple in
Wilmette.
Geysers of over were reported in both locations for up to an hour as the water was redistributed more evenly through the system. A system of watertight bulkheads has since been installed to prevent the event from occurring again.
During the
Chicago Flood of 1992, the water from the
Chicago River that leaked into the then-forgotten
underground freight tunnel system was eventually drained into the Deep Tunnel network, which itself was still under construction.
See also
★
Megaproject
★
Megastructure
Sources
★ Horan, D. (2005).
Deep Tunnel, Deep Ties. ''Chicago Tribune'', March 14, 2005 via
The Laborers Network. Retrieved December 23, 2005.
★
American Underground Association's Featured Project. ''American Underground Construction Association'', August 1999. Retrieved December 23, 2005.
★
Deep Tunnel Project. ''City of South Holland Website''. Retrieved December 23, 2005.
★ Schmidt, E. (2004).
Chicago's Tunnel, Reservoir Plan. ''McGraw-Hill Construction'', August 2004. Retrieved December 23, 2005.
★
Tunnel and Reservoir Plan (TARP). ''The Metropolitan Water Reclamation District of Greater Chicago'', August 6, 1999. Retrieved December 23, 2005.
★ Jones, S. and Waller, J. (2004).
Chicago Public Library - Down the Drain. ''Chicago Public Library website'', August 2004. Retrieved December 23, 2005.
References
External links
★
Metropolitan Water Reclamation District of Greater Chicago
★
Video of TARP on YouTube
★
Video of TARP on YuuTube
★
Article and Map in the Encyclopedia of Chicago